ERECTION OF DHDT REACTOR - 1300 MT - upgraded DEMAG CC 12000/SUPER LIFTER 1600

Get a Quote

MAKE YOUR PROJECT A SUCCESS WITH SUPERIOR SERVICES FROM THE LEADERS IN HEAVY LIFT ENGINEERING.

Innovative, smart & cost effective methodologies implemented for project execution at Vadinar

The Team completed the erection & installation of 3+6 Modules of the Derrick Supporting Structure & Derrick in Modules in the
Delayed Coker Unit (DCU) in a very Innovative way
• Normally, such structures are erected & installed in 6-8 months by
• Pre-Assembling the Frames
• Erecting the Frames
• Interconnecting the Beam
• Filling up all the Members
• The EPL Team innovated and completed the Structure in
• Entire Structure of 52 x 13 x 34 Mtrs was prepared in 3 Distinct Modules
• The Derrick Structure was prepared in 6 Distinct Modules
• All Modules were Fabricated, Assembled, Sand Blasted & Painted on ground
• The successful planning and implementation of this critical Erection & Installation Process, is reflected in the following facts:
Erection Three Structural Modules were erected within just 11 days & Six Derrick Modules within a month
• Perfect Designing & Detailing In a Span of 52 mts, there was an Actual Deflection of only only 5 mm
• Accurate Fabrication : A total 1760 Bolts – 160 Foundation & 1600 Splice Joint – were fitted within 4-5 hrs in the Column without
any hole enlargement
• Extraordinary Rigging : Module consisting of 1581 members was inserted between 4 Coke Drums through the small gaps of
150 mm
• Equipment This critical erection operation was completed using two cranes LR 1600 & Demag CC-6800